# IfcOpenShell - IFC toolkit and geometry engine
|
|
# Copyright (C) 2021 Dion Moult <dion@thinkmoult.com>
|
|
#
|
|
# This file is part of IfcOpenShell.
|
|
#
|
|
# IfcOpenShell is free software: you can redistribute it and/or modify
|
|
# it under the terms of the GNU Lesser General Public License as published by
|
|
# the Free Software Foundation, either version 3 of the License, or
|
|
# (at your option) any later version.
|
|
#
|
|
# IfcOpenShell is distributed in the hope that it will be useful,
|
|
# but WITHOUT ANY WARRANTY; without even the implied warranty of
|
|
# MERCHANTABILITY or FITNESS FOR A PARTICULAR PURPOSE. See the
|
|
# GNU Lesser General Public License for more details.
|
|
#
|
|
# You should have received a copy of the GNU Lesser General Public License
|
|
# along with IfcOpenShell. If not, see <http://www.gnu.org/licenses/>.
|
|
|
|
import ifcopenshell
|
|
import ifcopenshell.api.owner
|
|
import ifcopenshell.api.sequence
|
|
import ifcopenshell.guid
|
|
|
|
|
|
def assign_sequence(
|
|
file: ifcopenshell.file,
|
|
relating_process: ifcopenshell.entity_instance,
|
|
related_process: ifcopenshell.entity_instance,
|
|
sequence_type: str = "FINISH_START",
|
|
) -> ifcopenshell.entity_instance:
|
|
"""Assign a sequential relationship between tasks
|
|
|
|
Tasks in construction sequencing typically have sequence relationships
|
|
between them, indicating that one task must happen after another. This
|
|
is used to automatically compute new start and end dates and cascade
|
|
changes when dates are changed. This is also used to calculate critical
|
|
paths and floats.
|
|
|
|
There are four types of sequence relationships, known as finish to
|
|
start, finish to finish, start to start, and start to finish, sometimes
|
|
abbreviated as a (FS, FF, SS, and SF). The most common is the finish to
|
|
start relationship, indicating that the previous task must finish before
|
|
the next task can start.
|
|
|
|
You must not create cyclical task sequences. This makes the computer
|
|
unhappy.
|
|
|
|
Note that "previous" or "next" does not necessarily mean the task
|
|
chronologically happens before or after. They simply indicate the order
|
|
of the sequence relationship. For this reason, they are often called
|
|
predecessor and successor tasks in the planning profession.
|
|
|
|
:param relating_process: The previous / predecessor task.
|
|
:param related_process: The next / successor task.
|
|
:param sequence_type: Choose from FINISH_START, FINISH_FINISH,
|
|
START_START, or START_FINISH.
|
|
:return: The newly created IfcRelSequence
|
|
|
|
Example:
|
|
|
|
.. code:: python
|
|
|
|
# Let's imagine we are creating a construction schedule. All tasks
|
|
# need to be part of a work schedule.
|
|
schedule = ifcopenshell.api.sequence.add_work_schedule(model, name="Construction Schedule A")
|
|
|
|
# Let's imagine a root construction task
|
|
construction = ifcopenshell.api.sequence.add_task(model,
|
|
work_schedule=schedule, name="Construction", identification="C")
|
|
|
|
# Let's imagine we're doing a typically formwork, reinforcement,
|
|
# pour sequence. Let's start with the formwork. It'll take us 2
|
|
# days.
|
|
formwork = ifcopenshell.api.sequence.add_task(model,
|
|
parent_task=construction, name="Formwork", identification="C.1")
|
|
time = ifcopenshell.api.sequence.add_task_time(model, task=formwork)
|
|
ifcopenshell.api.sequence.edit_task_time(model,
|
|
task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"})
|
|
|
|
# Now let's do the reinforcement. It'll take us another 2 days.
|
|
reinforcement = ifcopenshell.api.sequence.add_task(model,
|
|
parent_task=construction, name="Reinforcement", identification="C.2")
|
|
time = ifcopenshell.api.sequence.add_task_time(model, task=reinforcement)
|
|
ifcopenshell.api.sequence.edit_task_time(model,
|
|
task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"})
|
|
|
|
# Now the pour it It'll only take 1 day.
|
|
pour = ifcopenshell.api.sequence.add_task(model,
|
|
parent_task=construction, name="Reinforcement", identification="C.3")
|
|
time = ifcopenshell.api.sequence.add_task_time(model, task=pour)
|
|
ifcopenshell.api.sequence.edit_task_time(model,
|
|
task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P1D"})
|
|
|
|
# Now let's say the formwork must finish before the reinforcement
|
|
# can start, and the reinforcement must finish before the pour can
|
|
# start. This is a typical finish to start relationship (FS).
|
|
ifcopenshell.api.sequence.assign_sequence(model,
|
|
relating_process=formwork, related_process=reinforcement)
|
|
ifcopenshell.api.sequence.assign_sequence(model,
|
|
relating_process=reinforcement, related_process=pour)
|
|
|
|
# Notice how we set all the scheduled start dates arbitrarily at
|
|
# 2000-01-01. This is because we can ask IfcOpenShell to
|
|
# automatically cascade the dates, starting from any task. This will
|
|
# update the reinforcement date to be 2000-01-03 and the pour date
|
|
# to be 2000-01-05.
|
|
ifcopenshell.api.sequence.cascade_schedule(model, task=formwork)
|
|
"""
|
|
for rel in related_process.IsSuccessorFrom or []:
|
|
if rel.RelatingProcess == relating_process:
|
|
return rel
|
|
rel = file.create_entity(
|
|
"IfcRelSequence",
|
|
**{
|
|
"GlobalId": ifcopenshell.guid.new(),
|
|
"OwnerHistory": ifcopenshell.api.owner.create_owner_history(file),
|
|
"RelatingProcess": relating_process,
|
|
"RelatedProcess": related_process,
|
|
"SequenceType": sequence_type,
|
|
}
|
|
)
|
|
ifcopenshell.api.sequence.cascade_schedule(file, task=relating_process)
|
|
return rel
|